ATWOOD AVENUE STREET IMPROVEMENTS PHASE II
INDIAN STREET TO PERRIS BOULEVARD

On February 10, 2003, roadway construction work is expected to begin along Atwood Avenue between Indian Street and Perris Boulevard. This project includes reconstruction and widening of the existing roadway with new asphalt pavement, curb and gutter, sidewalks, handicap ramps, storm drain installation and other ancillary improvements. Construction work hours are from 7:00 a.m. to 3:30 p.m. daily. Weather permitting; this street reconstruction work should be completed by May 2003.

Commuters are advised to take alternate routes to avoid this section of Atwood Avenue during the construction period. This project is being funded with Measure "A", Community Development Block Grant (CDBG) and Redevelopment Agency (RDA) funds.